The following message will appears when you first use the Primavera that you have just installed. This message means that you have not yet chosen what type of industry that will align with your project in Primavera.
For example: You are involved in an Oil and Gas project or a Manufacturing project or a Construction project.
This message will continue to appear when you log in Primavera until you select Indutri type.
To select Indutri type, on the Primavera page you access the following menu:
Admin -> Admin Preferences …
Select the Industry tab.
Choose the type of industry that suits your project.
When finished click Close.
The industry you choose causes P6 Professional to use terminology and default settings for calculations that most closely align with the selected industry.
Engineering and Construction: Determines the use of terminology and default settings for calculations aligned with the engineering and construction industries.
Government, Aerospace, and Defense: Determines the use of terminology and default settings for calculations aligned with government and with aerospace and defense industries.
High Tech, Manufacturing, and Others: Determines the use of terminology and default settings for calculations aligned with high-technology, manufacturing, and other industries.
Utilities, Oil, and Gas: Determines the use of terminology and default settings for calculations aligned with the utility, oil, and gas industries.
Industry Type | Industry Terminology Examples | Default startup window in P6 Professional |
Engineering and Construction | Budgeted Units Budgeted Cost Original Duration | Activities window |
Government, Aerospace, and Defense | Planned Units Planned Cost Planned Duration | Projects window |
High-Technology, Manufacturing | Planned Units Planned Cost Planned Duration | Projects window |
Utilities, Oil, and Gas | Budgeted Units Budgeted Cost Original Duration | Projects window |
- The Main Purpose of Official Project Scheduling - October 17, 2020
- RACI Matrix: Defenition, Benefits and How to Create - October 11, 2020
- Gantt Chart: Defenition, Examples and How to Create - October 6, 2020