How to Update Actual Project Progress in Primavera

The following is an example of project activities progress as of February 25, 2022:

Activity IDActivity NameStartedFinished%
  Design and Engineering   
    HP1000Design Building Addition1-Jul-211-Sep-21100%
    HP1010Start Office Building Addition Project1-Jul-21 100%
    HP1030Review and Approve Designs24-Aug-2117-Sep-21100%
    HP1050Assemble Technical Data for Heat Pump23-Sep-2129-Sep-21100%
    HP1160Review Technical Data on Heat Pumps28-Sep-2118-Oct-21100%
  Foundation   
    HP1090Begin Building Construction20-Sep-21 100%
    HP1100Site Preparation20-Sep-219-Nov-21100%
    HP1230Excavation11-Nov-2110-Dec-21100%
    HP1320Install Underground Water Lines8-Dec-2114-Dec-21100%
    HP1330Install Underground Electric Conduit3-Dec-2111-Dec-21100%
    HP1340Form/Pour Concrete Footings28-Dec-2127-Jan-22100%
    HP1350Concrete Foundation Walls1-Feb-22 70%
  Mechanical/Electrical Systems   
    HVAC    
      HP1190Prepare and Solicit Bids for Heat Pump21-Oct-216-Nov-21100%
      HP1240Review Bids for Heat Pump11-Nov-2121-Nov-21100%
      HP1270Award Contract for Heat Pump23-Nov-2130-Nov-21100%
      HP1290Fabricate and Deliver Heat Pump and Controls1-Dec-21 14%
  Exterior Finishes   
    Brick   
      HP1040Assemble Brick Samples20-Sep-21 100%
      HP1070Review and Approve Brick Samples20-Sep-2118-Oct-21100%
      HP1180Prepare and Solicit Bids for Brick Exterior19-Oct-214-Nov-21100%
      HP1220Review Bids for Brick5-Nov-2123-Nov-21100%
      HP1260Award Contract for Brick24-Nov-2129-Nov-21100%
      HP1280Deliver Brick30-Nov-2130-Nov-21100%
  Interior Finishes   
    Floor and Carpeting   
      HP1060Assemble and Submit Flooring Samples20-Sep-21 100%
      HP1080Review and Approve Flooring20-Sep-2118-Oct-21100%
      HP1170Prepare and Solicit Bids for Flooring19-Oct-2116-Nov-21100%
      HP1250Review Bids for Flooring18-Nov-214-Dec-21100%
      HP1300Award Contract for Flooring6-Dec-219-Dec-21100%
      HP1310Fabricate and Deliver Flooring10-Dec-21 23%

For ongoing Activities with Percent Complete Type Physical, as activity HP1350, fill in the Remaining Duration column with the remaining time required. The example for the HP1350 activity is filled with six days.

Also, read How to create a baseline in Primavera.

Otherwise, the remaining duration will be calculated automatically for activities that are still in progress using Percent Complete Type Duration (HP1290 and HP1310).

The steps to update the actual data, according to the data table above, are as follows:

  • Open the project to be updated. In this example, open the EC005011 Haitang Corporate Park project.
  • To fill in the actual date, select the activity for which you want to enter the actual date.
  • In the Details section, select the Status tab.
  • Click on the Checklist column in the Started section for activities that have started and the Finished column if the activity has been completed (completed).
Update-Actual-1
  • If your actual date is different from the planned date, you can change it by clicking on the three-dot box […] on the right side of the date and then selecting the actual date.
  • For activities that are still in progress enter only the start date, as below. To fill in the percentage of activity completion (HP1350), fill it in the Physical % column, or you can fill it in the Activity % Complete column. Fill in according to the progress of the activity.
Update-Actual-2

Note: The % Complete type will match one of the percent Complete types you selected, which are: Duration, Physical, or Units.

Update-Actual-3

If your choice is Duration, then the display in the Details -> Status section, as below:

Update-Actual-4

If your choice is Physical, then the display in the Details -> Status section, as below:

Update-Actual-5

If your choice is Units, then the display in the Details -> Status section, as below:

Update-Actual-6
  • Continue to fill in the actual data as shown in the table below.
  • At the HP1100 activity on the STEP tab, check the Completed column by clicking on it. Also, fill in the actual data (Started, Finished) and % Progress according to the data given in the table.
Update-Actual-7
  • Enter the Auto Compute Actuals column in the activity table. If activities have the same actual date as the Baseline date (initial plan), click on the Auto Compute Actuals column.
Update-Actual-8

If you do not click on the Auto Compute Actuals column, then the activities that which actual date has not been filled in and the baseline date is less than the Cutoff Date will shift to the same as the Cutoff Date (New Data Date) + 1 day, after the Apply Actuals.

For example, if the activity has not started yet, the plan will start one day after the cutoff date (October 31, 2021, will start on November 1, 2021). Or, if the activity is still in progress, the remaining duration will be calculated from the cutoff date.

The difference between Apply Actuals and Schedule [F9] is that all activity dates on the Apply Actuals that do not contain the actual date will be shifted to one day after the cutoff date (rather than sequentially according to the relationship), as shown in the example image below:

Update-Actual-9

While in Schedule [F9], all activities will shift according to their relationship (sequential) starting from the scheduling date, as shown in the example below:

Update-Actual-10
  • Next go to Tools menu -> Apply Actuals…, fill in the New Data Date column with February 25, 2022. This date is the actual Cuttoff Date date. After that, click the Apply button.

The results are as follows:

Update-Actual-12

• Then, you can reschedule (Tools -> Schedule…) using the Cutoff Date (Current Data Date) on February 25, 2022.

Update-Actual-13

Result:

Also, read step by step tutorial Primavera.